Water supply
Redevelopment of former barracks site

Special requirements for the drinking and extinguishing water supply of a barracks site with partial or full occupancy by soldiers: Problem of contamination in the water supply network, securing the supply of extinguishing water. Hydraulic recalculation of water supply network. Cistern installation.

Water supply
Redevelopment of former barracks site

Special requirements for the drinking and extinguishing water supply of a barracks site with partial or full occupancy by soldiers: Problem of contamination in the water supply network, securing the supply of extinguishing water. Hydraulic recalculation of water supply network. Cistern installation.

Transport facilities
Redesign of a city street in the Rhine-Main area

The client defined increasing the quality of stay as the most important criterion for the redesign. In close co-operation with landscape architects, we were responsible for road construction planning and construction supervision.

Transport facilities
Redesign of a city street in the Rhine-Main area

The client defined increasing the quality of stay as the most important criterion for the redesign. In close co-operation with landscape architects, we were responsible for road construction planning and construction supervision.

Transport facilities
Redesign of a city street in the Rhine-Main area

The client defined increasing the quality of stay as the most important criterion for the redesign. In close co-operation with landscape architects, we were responsible for road construction planning and construction supervision.

Transport facilities
Redesign of a city street in the Rhine-Main area

The client defined increasing the quality of stay as the most important criterion for the redesign. In close co-operation with landscape architects, we were responsible for road construction planning and construction supervision.

Transport facilities
Redesign of a city street in the Rhine-Main area

The client defined increasing the quality of stay as the most important criterion for the redesign. In close co-operation with landscape architects, we were responsible for road construction planning and construction supervision.

Transport facilities
Redesign of a city street in the Rhine-Main area

The client defined increasing the quality of stay as the most important criterion for the redesign. In close co-operation with landscape architects, we were responsible for road construction planning and construction supervision.

Transport facilities
Redesign of a city street in the Rhine-Main area

The client defined increasing the quality of stay as the most important criterion for the redesign. In close co-operation with landscape architects, we were responsible for road construction planning and construction supervision.

Transport facilities
Urban planning design of a town centre

Upgrading and creation of a high-quality recreational area in the town centre for a wide range of requirements for young and old in the community. Close cooperation with landscape planners and municipal committees in a challenging realisation period – completed in time for the 700th anniversary.

Transport facilities
Urban planning design of a town centre

Upgrading and creation of a high-quality recreational area in the town centre for a wide range of requirements for young and old in the community. Close cooperation with landscape planners and municipal committees in a challenging realisation period – completed in time for the 700th anniversary.

Transport facilities
Urban planning design of a town centre

Upgrading and creation of a high-quality recreational area in the town centre for a wide range of requirements for young and old in the community. Close cooperation with landscape planners and municipal committees in a challenging realisation period – completed in time for the 700th anniversary.

Transport facilities
Urban planning design of a town centre

Upgrading and creation of a high-quality recreational area in the town centre for a wide range of requirements for young and old in the community. Close cooperation with landscape planners and municipal committees in a challenging realisation period – completed in time for the 700th anniversary.

Transport facilities
Urban planning design of a town centre

Upgrading and creation of a high-quality recreational area in the town centre for a wide range of requirements for young and old in the community. Close cooperation with landscape planners and municipal committees in a challenging realisation period – completed in time for the 700th anniversary.

Transport facilities
Urban planning design of a town centre

Upgrading and creation of a high-quality recreational area in the town centre for a wide range of requirements for young and old in the community. Close cooperation with landscape planners and municipal committees in a challenging realisation period – completed in time for the 700th anniversary.

Transport facilities
Urban planning design of a town centre

Upgrading and creation of a high-quality recreational area in the town centre for a wide range of requirements for young and old in the community. Close cooperation with landscape planners and municipal committees in a challenging realisation period – completed in time for the 700th anniversary.

Transport facilities
Bypass with avoidance of earth transport

The measure was temporarily financed by the municipality until the project was budgeted by the state. To avoid landfill costs, we planned with a digital terrain model (DTM) and were able to equalise all earth movements on site.

Transport facilities
Bypass with avoidance of earth transport

The measure was temporarily financed by the municipality until the project was budgeted by the state. To avoid landfill costs, we planned with a digital terrain model (DTM) and were able to equalise all earth movements on site.

Transport facilities
Bypass with avoidance of earth transport

The measure was temporarily financed by the municipality until the project was budgeted by the state. To avoid landfill costs, we planned with a digital terrain model (DTM) and were able to equalise all earth movements on site.

Transport facilities
Bypass with avoidance of earth transport

The measure was temporarily financed by the municipality until the project was budgeted by the state. To avoid landfill costs, we planned with a digital terrain model (DTM) and were able to equalise all earth movements on site.

Transport facilities
Bypass with avoidance of earth transport

The measure was temporarily financed by the municipality until the project was budgeted by the state. To avoid landfill costs, we planned with a digital terrain model (DTM) and were able to equalise all earth movements on site.

Water supply
Refurbishment of drinking water tank Main-Kinzig district

The ageing 2,000 cubic metre spectacle container was completely refurbished in terms of construction and machinery following an inventory. Our services comprised the technical equipment including all ventilation and metal construction work as well as construction supervision.

Water supply
Refurbishment of drinking water tank Main-Kinzig district

The ageing 2,000 cubic metre spectacle container was completely refurbished in terms of construction and machinery following an inventory. Our services comprised the technical equipment including all ventilation and metal construction work as well as construction supervision.

Water supply
Refurbishment of drinking water tank Main-Kinzig district

The ageing 2,000 cubic metre spectacle container was completely refurbished in terms of construction and machinery following an inventory. Our services comprised the technical equipment including all ventilation and metal construction work as well as construction supervision.

Water supply
Refurbishment of drinking water tank Main-Kinzig district

The ageing 2,000 cubic metre spectacle container was completely refurbished in terms of construction and machinery following an inventory. Our services comprised the technical equipment including all ventilation and metal construction work as well as construction supervision.

Water supply
Refurbishment of drinking water tank Main-Kinzig district

The ageing 2,000 cubic metre spectacle container was completely refurbished in terms of construction and machinery following an inventory. Our services comprised the technical equipment including all ventilation and metal construction work as well as construction supervision.

Water supply
Refurbishment of drinking water tank Main-Kinzig district

The ageing 2,000 cubic metre spectacle container was completely refurbished in terms of construction and machinery following an inventory. Our services comprised the technical equipment including all ventilation and metal construction work as well as construction supervision.

Water supply
Refurbishment of drinking water tank Main-Kinzig district

The ageing 2,000 cubic metre spectacle container was completely refurbished in terms of construction and machinery following an inventory. Our services comprised the technical equipment including all ventilation and metal construction work as well as construction supervision.

Transport facilities
Petrol station and service area on the motorway

Planning of the entire service area for cars and lorries, including the drainage system.
Our engineering services included the integration of a kiosk facility in the car park as well as the entire coordination with the neighbouring municipality and utility companies.

Transport facilities
Petrol station and service area on the motorway

Planning of the entire service area for cars and lorries, including the drainage system.
Our engineering services included the integration of a kiosk facility in the car park as well as the entire coordination with the neighbouring municipality and utility companies.

Transport facilities
Petrol station and service area on the motorway

Planning of the entire service area for cars and lorries, including the drainage system.
Our engineering services included the integration of a kiosk facility in the car park as well as the entire coordination with the neighbouring municipality and utility companies.

Transport facilities
Petrol station and service area on the motorway

Planning of the entire service area for cars and lorries, including the drainage system.
Our engineering services included the integration of a kiosk facility in the car park as well as the entire coordination with the neighbouring municipality and utility companies.

Waste water
Canal renewal in the centre of Frankfurt

To maintain ongoing traffic, we planned the renewal of the combined sewer 5 metres below a narrow and busy road using a tunnel construction method. We were responsible for all planning phases in accordance with HOAI, including a tunnelling expert opinion. 

Waste water
Canal renewal in the centre of Frankfurt

To maintain ongoing traffic, we planned the renewal of the combined sewer 5 metres below a narrow and busy road using a tunnel construction method. We were responsible for all planning phases in accordance with HOAI, including a tunnelling expert opinion. 

Waste water
Canal renewal in the centre of Frankfurt

To maintain ongoing traffic, we planned the renewal of the combined sewer 5 metres below a narrow and busy road using a tunnel construction method. We were responsible for all planning phases in accordance with HOAI, including a tunnelling expert opinion. 

Waste water
Canal renewal in the centre of Frankfurt

To maintain ongoing traffic, we planned the renewal of the combined sewer 5 metres below a narrow and busy road using a tunnel construction method. We were responsible for all planning phases in accordance with HOAI, including a tunnelling expert opinion. 

Waste water
Canal renewal in the centre of Frankfurt

To maintain ongoing traffic, we planned the renewal of the combined sewer 5 metres below a narrow and busy road using a tunnel construction method. We were responsible for all planning phases in accordance with HOAI, including a tunnelling expert opinion. 

Waste water
Canal renewal in the centre of Frankfurt

To maintain ongoing traffic, we planned the renewal of the combined sewer 5 metres below a narrow and busy road using a tunnel construction method. We were responsible for all planning phases in accordance with HOAI, including a tunnelling expert opinion. 

Waste water
Canal renewal in the centre of Frankfurt

To maintain ongoing traffic, we planned the renewal of the combined sewer 5 metres below a narrow and busy road using a tunnel construction method. We were responsible for all planning phases in accordance with HOAI, including a tunnelling expert opinion. 

Waste water
Canal renewal in the centre of Frankfurt

To maintain ongoing traffic, we planned the renewal of the combined sewer 5 metres below a narrow and busy road using a tunnel construction method. We were responsible for all planning phases in accordance with HOAI, including a tunnelling expert opinion. 

Waste water
Canal renewal in the centre of Frankfurt

To maintain ongoing traffic, we planned the renewal of the combined sewer 5 metres below a narrow and busy road using a tunnel construction method. We were responsible for all planning phases in accordance with HOAI, including a tunnelling expert opinion. 

Hydraulic engineering
Flood protection: Alluvial material traps and inlet structures

Overall assessment of the problematic flood situation: Creation of alluvial material traps in higher forest areas to retain branches and foliage at the point of incidence of the watercourse up to inlet structures in the valley with 2 chambers for increased flood protection.

Hydraulic engineering
Flood protection: Alluvial material traps and inlet structures

Overall assessment of the problematic flood situation: Creation of alluvial material traps in higher forest areas to retain branches and foliage at the point of incidence of the watercourse up to inlet structures in the valley with 2 chambers for increased flood protection.

Hydraulic engineering
Flood protection: Alluvial material traps and inlet structures

Overall assessment of the problematic flood situation: Creation of alluvial material traps in higher forest areas to retain branches and foliage at the point of incidence of the watercourse up to inlet structures in the valley with 2 chambers for increased flood protection.

Hydraulic engineering
Flood protection: Alluvial material traps and inlet structures

Overall assessment of the problematic flood situation: Creation of alluvial material traps in higher forest areas to retain branches and foliage at the point of incidence of the watercourse up to inlet structures in the valley with 2 chambers for increased flood protection.

Hydraulic engineering
Flood protection: Alluvial material traps and inlet structures

Overall assessment of the problematic flood situation: Creation of alluvial material traps in higher forest areas to retain branches and foliage at the point of incidence of the watercourse up to inlet structures in the valley with 2 chambers for increased flood protection.

Hydraulic engineering
Flood protection: Alluvial material traps and inlet structures

Overall assessment of the problematic flood situation: Creation of alluvial material traps in higher forest areas to retain branches and foliage at the point of incidence of the watercourse up to inlet structures in the valley with 2 chambers for increased flood protection.

Development
Digital infrastructure: data centres Rhine-Main area

The special expertise of our engineering office includes the planning of complex piping systems and traffic infrastructure within the floor space of data centres. With highly specialised partners, we have been able to support 14 projects for international consortia for more than 10 years. The complexity is realised with BIM and REVIT.

Development
Digital infrastructure: data centres Rhine-Main area

The special expertise of our engineering office includes the planning of complex piping systems and traffic infrastructure within the floor space of data centres. With highly specialised partners, we have been able to support 14 projects for international consortia for more than 10 years. The complexity is realised with BIM and REVIT.

Development
Digital infrastructure: data centres Rhine-Main area

The special expertise of our engineering office includes the planning of complex piping systems and traffic infrastructure within the floor space of data centres. With highly specialised partners, we have been able to support 14 projects for international consortia for more than 10 years. The complexity is realised with BIM and REVIT.

Development
New residential area in the district of Giessen

Special challenges: Planning in water protection zone 3; integration of a rainwater retention basin in a moving topography. Intensive co-operation with all partners to meet the client’s demanding deadlines.

Development
New residential area in the district of Giessen

Special challenges: Planning in water protection zone 3; integration of a rainwater retention basin in a moving topography. Intensive co-operation with all partners to meet the client’s demanding deadlines.

Development
New residential area in the district of Giessen

Special challenges: Planning in water protection zone 3; integration of a rainwater retention basin in a moving topography. Intensive co-operation with all partners to meet the client’s demanding deadlines.

Development
New residential area in the district of Giessen

Special challenges: Planning in water protection zone 3; integration of a rainwater retention basin in a moving topography. Intensive co-operation with all partners to meet the client’s demanding deadlines.

Development
New residential area in the district of Giessen

Special challenges: Planning in water protection zone 3; integration of a rainwater retention basin in a moving topography. Intensive co-operation with all partners to meet the client’s demanding deadlines.

Development
New residential area in the district of Giessen

Special challenges: Planning in water protection zone 3; integration of a rainwater retention basin in a moving topography. Intensive co-operation with all partners to meet the client’s demanding deadlines.

Development
New residential area in the district of Giessen

Special challenges: Planning in water protection zone 3; integration of a rainwater retention basin in a moving topography. Intensive co-operation with all partners to meet the client’s demanding deadlines.

Sewer renovation
House connection liner

With our certified sewer rehabilitation consultants, Barthauer software and the use of the latest methods, we plan particularly economical solutions for trenchless rehabilitation with inliners, which can be carried out from houses directly via existing manholes.

Sewer renovation
House connection liner

With our certified sewer rehabilitation consultants, Barthauer software and the use of the latest methods, we plan particularly economical solutions for trenchless rehabilitation with inliners, which can be carried out from houses directly via existing manholes.

Sewer renovation
House connection liner

With our certified sewer rehabilitation consultants, Barthauer software and the use of the latest methods, we plan particularly economical solutions for trenchless rehabilitation with inliners, which can be carried out from houses directly via existing manholes.

Sewer renovation
House connection liner

With our certified sewer rehabilitation consultants, Barthauer software and the use of the latest methods, we plan particularly economical solutions for trenchless rehabilitation with inliners, which can be carried out from houses directly via existing manholes.

Sewer renovation
House connection liner

With our certified sewer rehabilitation consultants, Barthauer software and the use of the latest methods, we plan particularly economical solutions for trenchless rehabilitation with inliners, which can be carried out from houses directly via existing manholes.

Transport facilities
Final road extension for approx. 12 hectares of industrial estate

We planned the transport infrastructure in close consultation with the companies and ensured accessibility during the construction work to manage the delivery and private transport of the companies located here and to meet future requirements.

Transport facilities
Final road extension for approx. 12 hectares of industrial estate

We planned the transport infrastructure in close consultation with the companies and ensured accessibility during the construction work to manage the delivery and private transport of the companies located here and to meet future requirements.

Transport facilities
Final road extension for approx. 12 hectares of industrial estate

We planned the transport infrastructure in close consultation with the companies and ensured accessibility during the construction work to manage the delivery and private transport of the companies located here and to meet future requirements.

Transport facilities
Major city centre project in the Rhine-Main region

Upgrading of public traffic areas by redesigning the street space. Planning of complex junctions with consideration of cycle and pedestrian traffic and public green spaces. We were responsible for all service phases of the HOAI – from basic evaluation to acceptance.

Transport facilities
Major city centre project in the Rhine-Main region

Upgrading of public traffic areas by redesigning the street space. Planning of complex junctions with consideration of cycle and pedestrian traffic and public green spaces. We were responsible for all service phases of the HOAI – from basic evaluation to acceptance.

Transport facilities
Major city centre project in the Rhine-Main region

Upgrading of public traffic areas by redesigning the street space. Planning of complex junctions with consideration of cycle and pedestrian traffic and public green spaces. We were responsible for all service phases of the HOAI – from basic evaluation to acceptance.

Transport facilities
Major city centre project in the Rhine-Main region

Upgrading of public traffic areas by redesigning the street space. Planning of complex junctions with consideration of cycle and pedestrian traffic and public green spaces. We were responsible for all service phases of the HOAI – from basic evaluation to acceptance.

Transport facilities
Road renewal, pipe jacking, local heating network

Comprehensive engineering services for an 8 million investment project in the centre of the University city of Giessen. We planned with 10 engineers and CAD designers in 9 months and a construction time of 20 months. Difficult conditions required the use of many special processes.

Transport facilities
Road renewal, pipe jacking, local heating network

Comprehensive engineering services for an 8 million investment project in the centre of the University city of Giessen. We planned with 10 engineers and CAD designers in 9 months and a construction time of 20 months. Difficult conditions required the use of many special processes.

Transport facilities
Road renewal, pipe jacking, local heating network

Comprehensive engineering services for an 8 million investment project in the centre of the University city of Giessen. We planned with 10 engineers and CAD designers in 9 months and a construction time of 20 months. Difficult conditions required the use of many special processes.

Transport facilities
Road renewal, pipe jacking, local heating network

Comprehensive engineering services for an 8 million investment project in the centre of the University city of Giessen. We planned with 10 engineers and CAD designers in 9 months and a construction time of 20 months. Difficult conditions required the use of many special processes.

Transport facilities
Road renewal, pipe jacking, local heating network

Comprehensive engineering services for an 8 million investment project in the centre of the University city of Giessen. We planned with 10 engineers and CAD designers in 9 months and a construction time of 20 months. Difficult conditions required the use of many special processes.

Transport facilities
Road renewal, pipe jacking, local heating network

Comprehensive engineering services for an 8 million investment project in the centre of the University city of Giessen. We planned with 10 engineers and CAD designers in 9 months and a construction time of 20 months. Difficult conditions required the use of many special processes.

Transport facilities
Road renewal, pipe jacking, local heating network

Comprehensive engineering services for an 8 million investment project in the centre of the University city of Giessen. We planned with 10 engineers and CAD designers in 9 months and a construction time of 20 months. Difficult conditions required the use of many special processes.

Transport facilities
Road renewal, pipe jacking, local heating network

Comprehensive engineering services for an 8 million investment project in the centre of the University city of Giessen. We planned with 10 engineers and CAD designers in 9 months and a construction time of 20 months. Difficult conditions required the use of many special processes.

Transport facilities
Road renewal, pipe jacking, local heating network

Comprehensive engineering services for an 8 million investment project in the centre of the University city of Giessen. We planned with 10 engineers and CAD designers in 9 months and a construction time of 20 months. Difficult conditions required the use of many special processes.

Transport facilities
Fundamental renewal of a cramped local thoroughfare

The entire project had to be carried out due to the narrow, historically evolved town thoroughfare. The neighbours were informed and involved in meetings. We planned the road and all supply/utility lines in close consultation with the utility companies.

Transport facilities
Fundamental renewal of a cramped local thoroughfare

The entire project had to be carried out due to the narrow, historically evolved town thoroughfare. The neighbours were informed and involved in meetings. We planned the road and all supply/utility lines in close consultation with the utility companies.

Transport facilities
Fundamental renewal of a cramped local thoroughfare

The entire project had to be carried out due to the narrow, historically evolved town thoroughfare. The neighbours were informed and involved in meetings. We planned the road and all supply/utility lines in close consultation with the utility companies.

Water supply
Partial refurbishment of the Palmengarten Frankfurt

As part of a Europe-wide invitation to tender, we were commissioned to carry out a survey, renovation planning and other engineering services. The particular challenge is to protect the historic trees and the park with a largely trenchless construction method. And above all to reduce the considerable water losses. It was also important to ensure that visitors experienced as little disruption as possible. The 3rd of a total of 5 construction phases has already been realised.

Water supply
Partial refurbishment of the Palmengarten Frankfurt

As part of a Europe-wide invitation to tender, we were commissioned to carry out a survey, renovation planning and other engineering services. The particular challenge is to protect the historic trees and the park with a largely trenchless construction method. And above all to reduce the considerable water losses. It was also important to ensure that visitors experienced as little disruption as possible. The 3rd of a total of 5 construction phases has already been realised.

Water supply
Partial refurbishment of the Palmengarten Frankfurt

As part of a Europe-wide invitation to tender, we were commissioned to carry out a survey, renovation planning and other engineering services. The particular challenge is to protect the historic trees and the park with a largely trenchless construction method. And above all to reduce the considerable water losses. It was also important to ensure that visitors experienced as little disruption as possible. The 3rd of a total of 5 construction phases has already been realised.

Water supply
Partial refurbishment of the Palmengarten Frankfurt

As part of a Europe-wide invitation to tender, we were commissioned to carry out a survey, renovation planning and other engineering services. The particular challenge is to protect the historic trees and the park with a largely trenchless construction method. And above all to reduce the considerable water losses. It was also important to ensure that visitors experienced as little disruption as possible. The 3rd of a total of 5 construction phases has already been realised.

Water supply
Partial refurbishment of the Palmengarten Frankfurt

As part of a Europe-wide invitation to tender, we were commissioned to carry out a survey, renovation planning and other engineering services. The particular challenge is to protect the historic trees and the park with a largely trenchless construction method. And above all to reduce the considerable water losses. It was also important to ensure that visitors experienced as little disruption as possible. The 3rd of a total of 5 construction phases has already been realised.

Water supply
Partial refurbishment of the Palmengarten Frankfurt

As part of a Europe-wide invitation to tender, we were commissioned to carry out a survey, renovation planning and other engineering services. The particular challenge is to protect the historic trees and the park with a largely trenchless construction method. And above all to reduce the considerable water losses. It was also important to ensure that visitors experienced as little disruption as possible. The 3rd of a total of 5 construction phases has already been realised.

Water supply
Partial refurbishment of the Palmengarten Frankfurt

As part of a Europe-wide invitation to tender, we were commissioned to carry out a survey, renovation planning and other engineering services. The particular challenge is to protect the historic trees and the park with a largely trenchless construction method. And above all to reduce the considerable water losses. It was also important to ensure that visitors experienced as little disruption as possible. The 3rd of a total of 5 construction phases has already been realised.

Water supply
Partial refurbishment of the Palmengarten Frankfurt

As part of a Europe-wide invitation to tender, we were commissioned to carry out a survey, renovation planning and other engineering services. The particular challenge is to protect the historic trees and the park with a largely trenchless construction method. And above all to reduce the considerable water losses. It was also important to ensure that visitors experienced as little disruption as possible. The 3rd of a total of 5 construction phases has already been realised.

Water supply
Partial refurbishment of the Palmengarten Frankfurt

As part of a Europe-wide invitation to tender, we were commissioned to carry out a survey, renovation planning and other engineering services. The particular challenge is to protect the historic trees and the park with a largely trenchless construction method. And above all to reduce the considerable water losses. It was also important to ensure that visitors experienced as little disruption as possible. The 3rd of a total of 5 construction phases has already been realised.

Water supply
Partial refurbishment of the Palmengarten Frankfurt

As part of a Europe-wide invitation to tender, we were commissioned to carry out a survey, renovation planning and other engineering services. The particular challenge is to protect the historic trees and the park with a largely trenchless construction method. And above all to reduce the considerable water losses. It was also important to ensure that visitors experienced as little disruption as possible. The 3rd of a total of 5 construction phases has already been realised.

Water supply
Partial refurbishment of the Palmengarten Frankfurt

As part of a Europe-wide invitation to tender, we were commissioned to carry out a survey, renovation planning and other engineering services. The particular challenge is to protect the historic trees and the park with a largely trenchless construction method. And above all to reduce the considerable water losses. It was also important to ensure that visitors experienced as little disruption as possible. The 3rd of a total of 5 construction phases has already been realised.

Transport facilities
2 roundabouts and parallel cycle path connection

Planning of the construction project in the flood protection area and special topographical requirements. Determination of retention area loss with digital terrain model (DTM) and water level calculation. Significant increase in road user safety.

Transport facilities
2 roundabouts and parallel cycle path connection

Planning of the construction project in the flood protection area and special topographical requirements. Determination of retention area loss with digital terrain model (DTM) and water level calculation. Significant increase in road user safety.

Transport facilities
2 roundabouts and parallel cycle path connection

Planning of the construction project in the flood protection area and special topographical requirements. Determination of retention area loss with digital terrain model (DTM) and water level calculation. Significant increase in road user safety.

Engineering services
Redesign of historic market square

In cooperation with landscape architects and monument conservationists, comprehensive redesign and planning of the market square, fountain system with water features, local heating network, house connections, historic paving and installation of preserved stones, barrier-free paved areas.

Engineering services
Redesign of historic market square

In cooperation with landscape architects and monument conservationists, comprehensive redesign and planning of the market square, fountain system with water features, local heating network, house connections, historic paving and installation of preserved stones, barrier-free paved areas.

Engineering services
Redesign of historic market square

In cooperation with landscape architects and monument conservationists, comprehensive redesign and planning of the market square, fountain system with water features, local heating network, house connections, historic paving and installation of preserved stones, barrier-free paved areas.

Engineering services
Redesign of historic market square

In cooperation with landscape architects and monument conservationists, comprehensive redesign and planning of the market square, fountain system with water features, local heating network, house connections, historic paving and installation of preserved stones, barrier-free paved areas.

Engineering services
New siphon line for the Perfstausee

Joint project with a hydraulics specialist: planning and realisation of a new siphon line for dry weather drainage. The siphon line ensures a constant outflow to supply the downstream receiving watercourse with sufficient water for the vegetation and fish.

Engineering services
New siphon line for the Perfstausee

Joint project with a hydraulics specialist: planning and realisation of a new siphon line for dry weather drainage. The siphon line ensures a constant outflow to supply the downstream receiving watercourse with sufficient water for the vegetation and fish.

Engineering services
New siphon line for the Perfstausee

Joint project with a hydraulics specialist: planning and realisation of a new siphon line for dry weather drainage. The siphon line ensures a constant outflow to supply the downstream receiving watercourse with sufficient water for the vegetation and fish.

Engineering services
New siphon line for the Perfstausee

Joint project with a hydraulics specialist: planning and realisation of a new siphon line for dry weather drainage. The siphon line ensures a constant outflow to supply the downstream receiving watercourse with sufficient water for the vegetation and fish.

Water supply
New long-distance water pipeline to Frankfurt

We planned the renovation of a 1 km long DN 700 mm steel pipeline. A 2nd degree body of water was crossed in open construction. The renovation includes the complete installation as well as the refurbishment of the water chambers. One challenge was to ensure that cathodic corrosion protection (CCP) was professionally applied.

Water supply
New long-distance water pipeline to Frankfurt

We planned the renovation of a 1 km long DN 700 mm steel pipeline. A 2nd degree body of water was crossed in open construction. The renovation includes the complete installation as well as the refurbishment of the water chambers. One challenge was to ensure that cathodic corrosion protection (CCP) was professionally applied.

Water supply
New long-distance water pipeline to Frankfurt

We planned the renovation of a 1 km long DN 700 mm steel pipeline. A 2nd degree body of water was crossed in open construction. The renovation includes the complete installation as well as the refurbishment of the water chambers. One challenge was to ensure that cathodic corrosion protection (CCP) was professionally applied.

Water supply
New long-distance water pipeline to Frankfurt

We planned the renovation of a 1 km long DN 700 mm steel pipeline. A 2nd degree body of water was crossed in open construction. The renovation includes the complete installation as well as the refurbishment of the water chambers. One challenge was to ensure that cathodic corrosion protection (CCP) was professionally applied.

Water supply
New long-distance water pipeline to Frankfurt

We planned the renovation of a 1 km long DN 700 mm steel pipeline. A 2nd degree body of water was crossed in open construction. The renovation includes the complete installation as well as the refurbishment of the water chambers. One challenge was to ensure that cathodic corrosion protection (CCP) was professionally applied.

Water supply
New long-distance water pipeline to Frankfurt

We planned the renovation of a 1 km long DN 700 mm steel pipeline. A 2nd degree body of water was crossed in open construction. The renovation includes the complete installation as well as the refurbishment of the water chambers. One challenge was to ensure that cathodic corrosion protection (CCP) was professionally applied.

Water supply
New long-distance water pipeline to Frankfurt

We planned the renovation of a 1 km long DN 700 mm steel pipeline. A 2nd degree body of water was crossed in open construction. The renovation includes the complete installation as well as the refurbishment of the water chambers. One challenge was to ensure that cathodic corrosion protection (CCP) was professionally applied.

Transport facilities
Cycle path planning and Biggesee roundabouts

We planned the accompanying measures as part of the renewal of the Sondern viaduct and developed a solution for a roundabout in a particularly confined space between the bank and the slope.
We are also planning the cycle path to Biggesee and across the viaduct.

Transport facilities
Cycle path planning and Biggesee roundabouts

We planned the accompanying measures as part of the renewal of the Sondern viaduct and developed a solution for a roundabout in a particularly confined space between the bank and the slope.
We are also planning the cycle path to Biggesee and across the viaduct.

Transport facilities
Cycle path planning and Biggesee roundabouts

We planned the accompanying measures as part of the renewal of the Sondern viaduct and developed a solution for a roundabout in a particularly confined space between the bank and the slope.
We are also planning the cycle path to Biggesee and across the viaduct.

Transport facilities
Cycle path planning and Biggesee roundabouts

We planned the accompanying measures as part of the renewal of the Sondern viaduct and developed a solution for a roundabout in a particularly confined space between the bank and the slope.
We are also planning the cycle path to Biggesee and across the viaduct.

Transport facilities
Cycle path planning and Biggesee roundabouts

We planned the accompanying measures as part of the renewal of the Sondern viaduct and developed a solution for a roundabout in a particularly confined space between the bank and the slope.
We are also planning the cycle path to Biggesee and across the viaduct.

Water supply
Rehabilitation of city centre drinking water pipeline

New construction of a shaft structure to separate various pressure pipe zones during ongoing operation. The switchover was carried out specifically at night to ensure security of supply without interruption.

Water supply
Rehabilitation of city centre drinking water pipeline

New construction of a shaft structure to separate various pressure pipe zones during ongoing operation. The switchover was carried out specifically at night to ensure security of supply without interruption.

Water supply
Rehabilitation of city centre drinking water pipeline

New construction of a shaft structure to separate various pressure pipe zones during ongoing operation. The switchover was carried out specifically at night to ensure security of supply without interruption.

Transport facilities
Planning cycle paths to increase road safety

We planned a complete new cycle path parallel to the busy main road on the motorway as a link from the service area to the city centre. A roundabout for cyclists and pedestrians was also integrated into the planning. Another element was the design of an insurance system to drain the surface water along the cycle path.

Transport facilities
Planning cycle paths to increase road safety

We planned a complete new cycle path parallel to the busy main road on the motorway as a link from the service area to the city centre. A roundabout for cyclists and pedestrians was also integrated into the planning. Another element was the design of an insurance system to drain the surface water along the cycle path.

Transport facilities
Planning cycle paths to increase road safety

We planned a complete new cycle path parallel to the busy main road on the motorway as a link from the service area to the city centre. A roundabout for cyclists and pedestrians was also integrated into the planning. Another element was the design of an insurance system to drain the surface water along the cycle path.

Development
Sophisticated new development area in Wetterau

The construction area was developed in 2 construction phases. The sale and development of the plots was completed within just two years. An appealing street design with a high level of attractiveness was created in the planning and execution.

Development
Sophisticated new development area in Wetterau

The construction area was developed in 2 construction phases. The sale and development of the plots was completed within just two years. An appealing street design with a high level of attractiveness was created in the planning and execution.

Development
Sophisticated new development area in Wetterau

The construction area was developed in 2 construction phases. The sale and development of the plots was completed within just two years. An appealing street design with a high level of attractiveness was created in the planning and execution.

Waste water
New sewage pumping station and pressure pipe

Due to the increased demands on purification performance, the existing sewage treatment plant will be decommissioned and replaced by a pumping station with a waste water pressure pipe and connection to a large existing sewage treatment plant.

Waste water
New sewage pumping station and pressure pipe

Due to the increased demands on purification performance, the existing sewage treatment plant will be decommissioned and replaced by a pumping station with a waste water pressure pipe and connection to a large existing sewage treatment plant.

Waste water
New sewage pumping station and pressure pipe

Due to the increased demands on purification performance, the existing sewage treatment plant will be decommissioned and replaced by a pumping station with a waste water pressure pipe and connection to a large existing sewage treatment plant.

Waste water
New sewage pumping station and pressure pipe

Due to the increased demands on purification performance, the existing sewage treatment plant will be decommissioned and replaced by a pumping station with a waste water pressure pipe and connection to a large existing sewage treatment plant.

Water supply
Refurbishment at Hessenpark Neu-Anspach

Due to numerous instances of damage to the water pipes in recent years, it was decided to replace them in order to ensure that the many events at the popular »Hessenpark« excursion destination can continue to take place. During the planning phase, we attached particular importance to minimising disruption for visitors. The implementation of the measures was therefore designed as a closed construction method.

Water supply
Refurbishment at Hessenpark Neu-Anspach

Due to numerous instances of damage to the water pipes in recent years, it was decided to replace them in order to ensure that the many events at the popular »Hessenpark« excursion destination can continue to take place. During the planning phase, we attached particular importance to minimising disruption for visitors. The implementation of the measures was therefore designed as a closed construction method.

Water supply
Refurbishment at Hessenpark Neu-Anspach

Due to numerous instances of damage to the water pipes in recent years, it was decided to replace them in order to ensure that the many events at the popular »Hessenpark« excursion destination can continue to take place. During the planning phase, we attached particular importance to minimising disruption for visitors. The implementation of the measures was therefore designed as a closed construction method.

Water supply
Refurbishment at Hessenpark Neu-Anspach

Due to numerous instances of damage to the water pipes in recent years, it was decided to replace them in order to ensure that the many events at the popular »Hessenpark« excursion destination can continue to take place. During the planning phase, we attached particular importance to minimising disruption for visitors. The implementation of the measures was therefore designed as a closed construction method.

Engineering services
Spring water pipeline through the centre of Frankfurt

The »Enkheimer Ried« flow connection was born as an idea in 1998 and was planned and realised by us after numerous planning variants. The selected variant includes: a total length of around 2 km; inner-city tunnelling; approx. 200 m inliner rehabilitation of a former DN 800 trench pipework; new pumping station using the lowering method; renaturation of a watercourse parcel.

Engineering services
Spring water pipeline through the centre of Frankfurt

The »Enkheimer Ried« flow connection was born as an idea in 1998 and was planned and realised by us after numerous planning variants. The selected variant includes: a total length of around 2 km; inner-city tunnelling; approx. 200 m inliner rehabilitation of a former DN 800 trench pipework; new pumping station using the lowering method; renaturation of a watercourse parcel.

Engineering services
Spring water pipeline through the centre of Frankfurt

The »Enkheimer Ried« flow connection was born as an idea in 1998 and was planned and realised by us after numerous planning variants. The selected variant includes: a total length of around 2 km; inner-city tunnelling; approx. 200 m inliner rehabilitation of a former DN 800 trench pipework; new pumping station using the lowering method; renaturation of a watercourse parcel.

Transport facilities
Residential street

The recently completed road upgrade creates safe and comfortable traffic conditions, especially for our youngest road users. The safety of pedestrians has been significantly improved by a levelled road extension. In addition, newly laid paved footpaths provide a clear demarcation between the carriageway and the pedestrian area, optimising orientation and safety for all road users.

Transport facilities
Residential street

The recently completed road upgrade creates safe and comfortable traffic conditions, especially for our youngest road users. The safety of pedestrians has been significantly improved by a levelled road extension. In addition, newly laid paved footpaths provide a clear demarcation between the carriageway and the pedestrian area, optimising orientation and safety for all road users.

Engineering services
Remodelling of Bahnhofstrasse

The measure was implemented as part of the »Städtebaulicher Denkmalschutz« federal state programme. The aim of the programme is to upgrade urban districts with a particular focus on design aspects. The entire project was realised in an extremely short time. (Visualisation: © Umbaustadt GbR Frankfurt am Main)

Engineering services
Remodelling of Bahnhofstrasse

The measure was implemented as part of the »Städtebaulicher Denkmalschutz« federal state programme. The aim of the programme is to upgrade urban districts with a particular focus on design aspects. The entire project was realised in an extremely short time. (Visualisation: © Umbaustadt GbR Frankfurt am Main)